Technical cover — air handling unit scheduling
Energy efficiency & smart buildings

Rescheduling Air Handling Units to Match Occupancy Patterns

Location
Riyadh
Period
2026
Status
In progress
Role
Leading the operational study, schedule design, and verification

Overview

Operational studies to redesign air handling unit schedules based on classroom occupancy patterns, aiming to cut unnecessary runtime hours while maintaining indoor environmental quality.

Legacy operating schedules are typically built around official working hours rather than the actual occupancy of the spaces. The gap between the two represents full operating hours with no beneficiary — waste that can be addressed through scheduling without any modification to the equipment.

Scheduling is the least costly energy-efficiency measure and the most prone to erosion. The value lies not in designing the schedule, but in locking it in and preventing it from reverting to what it was.

Responsibility

My role

  • Leading the operational study and analyzing actual occupancy patterns.
  • Designing an independent operating schedule for each zone instead of a unified schedule.
  • Defining pre-conditioning periods that preserve comfort at the start of occupancy.
  • Verifying air quality and comfort indicators after implementation.

Handling

Challenges & actions

Each challenge is linked directly to the action taken and its operational impact.

Challenge

A unified operating schedule that does not reflect the varying occupancy across facilities and classrooms.

Action

Building an independent schedule for each zone based on its actual occupancy pattern.

Impact

Reduced runtime hours in low-occupancy spaces.

Challenge

Events outside working hours that require exceptional operation.

Action

Adding a time-limited exceptional-operation mechanism that automatically reverts to the base schedule.

Impact

Accommodating exceptional demand without reverting to continuous operation.

Challenge

Manual adjustments that gradually erode the effect of scheduling.

Action

Locking the schedules within the control system and restricting edit privileges.

Impact

Stable settings after approval.

Summary

Lessons learned

  • 01

    Scheduling is the cheapest energy-efficiency measure: no equipment and no contractor, just tuning within an existing system.

  • 02

    Any measure not locked into the system erodes within months through manual adjustments.

Related projects

Energy efficiency & smart buildingsIn progressRiyadh

Separating Residential Buildings from Government Buildings via a Smart Electricity Metering System

An electrical infrastructure project to restructure metering in Faculty Members Housing: a field inventory of feed points and load assessment, and the installation of 1,134 smart meters in coordination with Saudi Energy (SE), with verification that each meter matched its point before approval — giving each building an independent reading on which billing and conservation programs can be built.

Role:Leading execution, coordination with the electricity service provider, and engineering supervision

View project details
Energy efficiency & smart buildingsIn progressRiyadh

Large-Scale Lighting Modernization Program | Specification Review, Illuminance Levels, and Performance

Led the technical review of a campus-wide lighting modernization program covering more than 1,000,000 lighting units: defining luminaire type and color temperature, reviewing specifications and illuminance levels for each space type, calculating expected savings, sequencing execution, and monitoring quality with field verification before approval.

Role:Technical review and approval: specifications, illuminance levels, color temperature, and quality assurance

View project details
Energy efficiency & smart buildingsIn progressRiyadh

Controlling Fan Coil Units (FCU) Based on Actual Occupancy

Designing an operating strategy based on the actual occupancy of fan coil units using PIR occupancy sensors, so that the system automatically controls operation according to actual presence.

Role:Designing the control strategy and supervising implementation and verification

View project details