Technical cover — large-scale lighting efficiency program
Energy efficiency & smart buildings

Large-Scale Lighting Modernization Program | Specification Review, Illuminance Levels, and Performance

Location
Riyadh
Period
2026
Status
In progress
Role
Technical review and approval: specifications, illuminance levels, color temperature, and quality assurance

Overview

Led the technical review of a campus-wide lighting modernization program covering more than 1,000,000 lighting units: defining luminaire type and color temperature, reviewing specifications and illuminance levels for each space type, calculating expected savings, sequencing execution, and monitoring quality with field verification before approval.

At a scale exceeding one million lighting units, the decision is not the choice of technology — LED technology is settled — but the technical review: which specifications and color temperatures to approve, which illuminance levels to require for each space type, in what order the phases are executed, and how quality is controlled before deviation propagates across the entire scope.

At a scale exceeding one million lighting units, the challenge is not the technology — LED technology is settled — but the technical review of a program this size: which specification and color temperature to approve, which illuminance level to require for each space, and in what order it is executed.

Approval before supply

Every lighting unit entering the program undergoes technical review and engineering approval: verifying specification compliance, confirming the unit’s suitability for the space type, and requiring the target illuminance level as an acceptance criterion rather than an indicative goal.

Sequencing is the decision

The unit that operates the longest hours yields the highest savings when modernized first. Building the sequence on baseline and operating-hours analysis, rather than on ease of access, is what determines the program’s actual return — and field verification of illuminance levels after installation is what ensures the savings were not achieved at the expense of lighting quality.

Responsibility

My role

  • Technical review of proposals and specifications and approval of luminaires before supply.
  • Specifying the required illuminance levels for each space type and adopting them as an acceptance criterion.
  • Building the execution sequence on operating-hours and expected-savings analysis rather than on ease of access.
  • Engineering supervision of the modernization work and field verification of compliance.
  • Quality assurance and resolving deviations before moving to the next phase.
  • Integrating outputs into the operation and maintenance cycle and monitoring post-modernization performance.

Execution

Project phases

01

Inventory and technical planning

Inventorying the existing lighting units and classifying them by type, location, and operating hours; analyzing the baseline; and building an execution sequence based on expected savings rather than ease of access.

Role: Leading the inventory methodology and approving execution priorities.

Outcome: An execution plan ordered by highest expected savings for each phase.

02

Execution and quality assurance

Engineering supervision of the modernization work, technical review of the supplied units, and field verification of the resulting illuminance levels in each space type before approving the phase.

Role: Engineering supervision, quality assurance, and field verification.

Outcome: Illuminance levels compliant with requirements before approving each phase.

Handling

Challenges & actions

Each challenge is linked directly to the action taken and its operational impact.

Challenge

Uneven illuminance levels after modernization in some space types.

Action

Reviewing the distribution and specifications of the units and correcting them before moving to the next locations.

Impact

Preventing the deviation from recurring across the entire program scope.

Challenge

A scope exceeding one million units, whose quality is difficult to control through random inspection.

Action

Adopting an inspection and acceptance methodology for each phase before closing it.

Impact

A unified acceptance reference instead of field judgment.

Impact

Results

Lighting unit
+1,000,000

Summary

Lessons learned

  • 01

    At scale, sequencing execution by operating hours yields higher savings than increasing the number of units replaced.

  • 02

    Quality control must precede expansion, not follow it.

  • 03

    The approved specification and the required illuminance level are what protect the program from quality decline under the pressure of volume.

Related projects

Energy efficiency & smart buildingsIn progressRiyadh

Separating Residential Buildings from Government Buildings via a Smart Electricity Metering System

An electrical infrastructure project to restructure metering in Faculty Members Housing: a field inventory of feed points and load assessment, and the installation of 1,134 smart meters in coordination with Saudi Energy (SE), with verification that each meter matched its point before approval — giving each building an independent reading on which billing and conservation programs can be built.

Role:Leading execution, coordination with the electricity service provider, and engineering supervision

View project details
Energy efficiency & smart buildingsIn progressRiyadh

Controlling Fan Coil Units (FCU) Based on Actual Occupancy

Designing an operating strategy based on the actual occupancy of fan coil units using PIR occupancy sensors, so that the system automatically controls operation according to actual presence.

Role:Designing the control strategy and supervising implementation and verification

View project details